Sentinel Building, Waterloo St, Glasgow

  • Sentinel Building, Waterloo St, Glasgow

Project Description

Refurbishment and redevelopment of a 2005 landmark office building situated in Glasgow’s City Centre, arranged over basement, ground and 9 upper levels. Works are being carried out in a ‘live’ environment with existing occupiers initially on ground, 1st, 2nd, 8th & 9th floor levels.

Phase 1 works include carrying out CAT A fit out works to unoccupied floors replacing raised access flooring, new suspended ceilings including new lighting; new M&E installations; new WCs; refurbishment of landlords core areas; extension and refurbishment of existing reception including introduction of feature ‘box’; creation of shower, changing and WC facilities in basement level; phased installation of 3 Nr lifts; replacement of external cladding. The occupier in 1st and 2nd floor levels vacated during the currency of the works and Phase 1A CAT A fit-out works were undertaken partly concurrently with Phase 1 works.

Our Role / Scope

Pre-Contract:
Involved through the feasibility stage to pre-contract stages. Responsible for assisting the Client and leading / managing the design team ensuring the design stages were completed within the deadlines within the master programme. Our role required the preparation and issue of tender documents along with tender reviews and a recommendation for Contractor appointment.

Post-Contract:
Works comprised weekly site visits to review progress, chairing monthly progress meetings, managing a change control process including agreeing costs with the contractor prior to issuing any variations to the contract and certifying payments to the contractor. Works have now completed on site. Liaison is ongoing with potential occupiers.

Benefits To Client

  • Multi-discipline commission utilising streamlined and consistent processes.
  • Extensive Contractual Knowledge of SBCC Suite of Contracts.

Client

Ardstone Capital

Role

Quantity Surveying, Project Management & Principal Designer

Value

Confidential

Programme

Phase 1 (Sections 1-3) November 2018 to October 2019   (Section 4) Completion March 2020  Phase 1A (Section 5) July 2019 to January 2020

Procurement

SBCC Traditional

Location

Glasgow