Broomhills Primary School

  • Broomhills Primary School

Project Description

Doig+Smith were engaged to deliver a further 3 Primary Schools following the successful procurement of St John’s Primary School under the CEC Framework.  One of these was a brand new offering to the South East of Edinburgh to complement new residential areas.  We recommended a bespoke procurement arrangement based on the Client’s key value drivers and  governmental best practice guidance. CEC welcomed this approach and enacted the procurement route on this and two other Primary Schools. The Supply Chain also welcomed the approach. Early engagement with Designers to detail the cost sensitive aspects and the site constraints / project abnormals, including the ground conditions delivered by providing developer.

The new school provides 2-stream Primary placement along with Nursery care.  The external works are extensive as the site is 1.9 Ha; this includes a 7-a-side pitch and hard/soft landscaping as well as playground and Nursery play areas.  The design takes account of most recent thoughts and guidance from various public bodies and education authorities, regarding space planning and teaching narrative.

Our Role / Scope

Full Quantity Surveying from very early outline benchmarking, to managing the commercial delivery of the various project aspects.

Technical Capacity

The team comprised of the following:

  • Project Director
  • Associate / Lead Quantity Surveyor
  • Quantity Surveyor

Benefits to Client

  • Expert knowledge from previous project deployed on follow-on project.
  • Applying specialist knowledge to practical applications, tailored specifically to Client requirements.
  • Comprehensive knowledge of the Client framework approach and how to garner the best from the supply chain involved.
  • Multiple project approach – live knowledge transfer from collaborative team.
  • Procurement programme remained flexible to enable pre-stage 2 sign off Client-driven changes. Once included, the proposed procurement method remained agile enough to still deliver to requirements.
  • Supply chain appetite for projects enhanced by Procurement selection.
  • Successful post contract Change Control.

Client

City of Edinburgh Council

Role

Quantity Surveying

Value

£12m

Programme

14 months construction

Procurement

Bespoke 2-Stage Traditional Work Package Call Off with Collaborative Early Engagement of Supply Chain

Location

North Lanarkshire